$15 Million W.Va. 2 Road Widening Project in Moundsville Moves Forward
Trending
MOUNDSVILLE -- A $15 million road widening project that began in early 2018 on the section of W.Va. 2 that stretches from Monarch Stadium in Moundsville to the U.S. 250/Jefferson Avenue extension is moving forward this week with bridge replacement work near Monarch Stadium.
In addition to creating two lanes that run the full length of the construction zone on both sides of W.Va. 2, a middle turning lane will be created as part of the overall project. The first of two small bridges, which spans a creek close to Monarch Stadium, is currently being replaced. A second bridge located closer to the Walmart entrance will completely be removed and a void filled in where a trail once existed.
West Virginia Division of Highways District 6 Construction Engineer Joe Juszczak said while most of the utility work in that area is nearly complete, the bridge replacement phase continues to progress. The concrete deck for the northbound lanes of the bridge closer to the stadium was poured last week.
He said the DOH expects to shift the traffic pattern to the northbound lanes on the new bridge by early summer and begin replacing the southbound side of the bridge.
"We hope to have the traffic switched to the new part of the bridge in June and then demo the opposite side and reconstruct that (side)," Juszczak said.
He noted that crews expect to begin demolishing the second bridge closer to the Walmart entrance sometime within the next six weeks. He said traffic will be maintained in both directions throughout the course of the project.
"We're still shooting for a completion date for the end of this year," Juszczak said.
He added that while most of the utility work is complete in the work zone, crews continue to install culvert drainage pipes in the area. Water and sewer lines were replaced in the designated work zone as part of the project contract, and gas and electric companies also moved or replaced utility lines within the work zone to accommodate the overall project, according to Juszczak.
Triton Construction Inc. of St. Albans, W.Va., is the general contractor for the project. DOH officials said expected project completion dates can change due to weather or other unforeseen circumstances.